Then saw from info received by OGE in Thai after visit of Pasquale seems to me that everything is OK, there is no need to ask or have more info, you know all what is the problem, and what are the solutions, then must be communicated to Sky Power when the person is going to do the changes, or if you send instructions as required by Sky Power to do the job for them,To put an end to the problems and put all of the 11 machines in tesserae conditions as those provided to OGE, calibration is only wasting time, change connecting rods, TAC, NRV and another, and the same thing for that supplied to BJVP which is located under the same conditions.
The problem had been to OGE is not tied to the machine but to change the parameters that has done DJ.Moreover, it is changed the connecting rod and the cross head a few months ago, but it was bought by us.
The other machines should have no problems but we do an update improvement including close valves input/output when the compressor is in stop.